§ 905.320. Contract administration and acceptance of work.

344 words·~2 min read·/us/cfr/t24/s§ 905.320·

A research copy — for the controlling text, always check the official state or federal source. Not legal advice.

(a)Contract administration. The PHA is responsible, in accordance with 2 CFR part 200, subpart D, for all contractual and administrative issues arising out of their procurements. The PHA shall maintain full and complete records on the history of each procurement transaction.
(b)Inspection and acceptance. The PHA, or, in the case of mixed finance, the Owner Entity shall carry out inspections of work in progress and goods delivered, as necessary, to ensure compliance with existing contracts. If, upon inspection, the PHA determines that the work and/or goods are complete, satisfactory and, as applicable, otherwise undamaged, except for any work that is appropriate for delayed completion, the PHA shall accept the work. The PHA shall determine any holdback for items of delayed completion and the amount due and payable for the work that has been accepted, including any conditions precedent to payment that are stated in the construction contract or contract of sale. The contractor shall be paid for items only after the PHA inspects and accepts that work.
(c)Guarantees and warranties. The PHA or, in the case of mixed finance, the Owner Entity, shall specify the guaranty period and amounts to be withheld, as applicable, and shall provide that all contractor, manufacturer, and supplier warranties required by the construction and modernization documents shall be assigned to the PHA. The PHA shall inspect each dwelling unit and the overall project approximately 3 months after the beginning of the project guaranty period, 3 months before its expiration, and at other times as may be necessary to exercise its rights before expiration of any warranties. The PHA shall require repair or replacement of all defective items prior to the expiration of the guaranty or warranty periods.
(d)Notification of completion. The PHA, or in the case of mixed finance, the Owner Entity, shall require that all contractors and developers notify the PHA in writing when the contract work, including any approved off-site work, will be completed and ready for inspection. \[78 FR 63770, Oct. 24, 2013, as amended at 80 FR 75942, Dec. 7, 2015\]
Connections1 off-index
1 reference not yet in our index
  • 2 CFR 200
Citation graph
cites case law
§ 905.320
Contract administration and acceptance of work.
Cite2 CFR 200
Cites 1Cited by 0 across 0 sources
★   the supreme law of the land   ★
Don't Tread on Me
E Pluribus Unum — out of many, one

"If you don't know your rights, you don't have any."

Marginalia · a citizen's law index
A research desk, not legal advice. Always read the cited source before relying on a summary.
Questions or an issue? support@self-law.org
disclaimerMarginalia is a research index, not a law firm. Nothing on this site is legal, tax, or financial advice and no attorney–client relationship is formed by using it. Statutes, regulations, and case law change; summaries, search results, AI output, and member posts may be incomplete, out of date, or wrong. Any interpretation drawn from material on this site should be validated by a licensed attorney in your jurisdiction before you act on it.